Feb 2026: Rear View of Air Hitam Lot 8631
Feb 2026: 1st Floor Beam & Slab Reinforcement Work in progress
Feb 2026: Ground Floor Slab Reinforcement Work In Progress
Feb 2026: Pilecap Excavation Work In Progress
Jan 2026: Lot 8 and Lot 7: Pilling works in progress
Jan 2026: Ground Beam Formwork Installation works in progress
1 Aug 2025: Road access & Landscape work in progress.
1 Aug 2025: Road access & Landscape work in progress.
1 July 2025: Road works in progress.
1 July 2025: Road works in progress.
1 July 2025: Road works in progress.
1 May 2025: Commencement of internal infrastructure works.
1 March 2025: Architectural work in progress.
1 February 2025: Architectural work in progress.
1 November 2024: Architectural work in progress.
1 June 2024: Main building works in progress.
1 January 2024: Surcharge removal in progress.
1 December 2023: Surcharge consolidation resting period.
1 November 2023: Surcharge consolidation & Piling work.
1 September 2023: Earthworks and ground treatment works.
1 August 2023: Earthwork & ground treatment works in progress.
30 June 2023: Earthwork & ground treatment works in progress.
1 May 2023: Earthwork & ground treatment works in progress.
1 April 2023: Platform filling works in progress.